Five 2024-bond capital-improvement packages head to bid
- Trade
- Capital / Bond Construction
- Meeting
- Nov 17, 2026
- Value
- Not stated in report
The November 2026 Executive Program Summary says packages P5 (Boren, Brown, Nash, Perry and Reid ES), P6 (Neal, Ponder, Rendon and Sheppard ES), P10 (Summit HS and Cross Timbers) and P13 (Lake Ridge HS, Lillard IS and McKinzey MS) "will be bid fall of 2026" for summer 2027 completion. P12 (Legacy HS and Shepard IS) is under review with Huckabee, and bid advertisement begins mid-December. GCs and MEP, roofing and finish subs should watch the district's bid postings.